The Washington Department of Ecology is accepting public comments on a draft cleanup plan for the USG Taylor Way Plant Site, a roughly nine-acre property along Tacoma’s Hylebos Waterway. The comment period opened Nov. 12 and closes at 11:59 p.m. Dec. 18. The site’s main address is 2301 Taylor Way.

The property was used to manufacture rock wool, a mineral-fiber insulation, from 1959 to 1973. Ecology says slag from ASARCO’s Tacoma copper smelter was used in production and contributed to arsenic, lead and other heavy metals in soil and groundwater. Contamination also affects two adjacent properties.

The Port of Tacoma and USG Interiors are identified as the parties responsible for conducting and paying for the cleanup. Ecology says more than 32,000 tons of soil and source material have already been removed over the past 30 years, along with earlier work such as storm-drain repairs, paving and groundwater monitoring.

The new draft plan proposes work in four areas, including more contaminated-soil excavation, a permeable reactive barrier near the waterway and protective caps in areas where contamination would otherwise remain near the surface. The plan also calls for additional investigation in one area before the final excavation design is set. Ecology says no final decision has been made.

Comments can be submitted online through the Department of Ecology, or by email or mail to the site manager. The agency says it will review public feedback before deciding whether to approve and finalize the plan. The full site documents and comment instructions are available through the Department Ecology.